Week Three

PUE were busy this week.

On Monday & Tuesday, they levelled, rammed and compressed the base within the box, built a temporary wooden frame, installed the damp-proof course and positioned the reinforcing metal mesh.

On Wednesday & Thursday, a constant stream of lorries brought the concrete and team barrowed and levelled this.

By the end of Friday, the foundations were done.