We’ve completed the inside painting of the two Stage One blocks, and are trying to ensure they do not feel ‘institutional’. Each studio is different, and the corridors are homely and attractive.
Here is one of the shared kitchens ready for the fittings to be installed… It’s easiest to fit the doors as the very last job – saves them from being marked…
Meanwhile, the walls have started to rise on the two Stage Two houses…
We’ve only two weeks left until our teachers have to vacate their rented shacks, so there will be frenetic activity to try to complete our two Stage One blocks by then. We can then work at a slightly more leisurely pace on the Stage Two houses.