Stage Three underway

In Stage Three, we are refurbishing and up-grading our existing block of four small two-bedroom homes.

We are making major internal structural adjustments to make better use of the space, and we are replumbing, rewiring, installing solar and bringing them up to the same standard of ‘improved living’ as the new homes in Stages One and Two.

We completed the first of the four homes during March, and are now working on the other three at the same time and hope to complete them by the end of May.